The structural, mechanical, piping (SMP) scope included the completion of the gas turbines 1 and 2; the completion of the piperacks and heavy wall steam pipe; and construction works on the HRSG’s (heat recovery steam generators) 1, 2 and 3, two steam turbines, two cooling towers as well as associated pipework.
Bulk Storage and
Materials Handling
STRUCTURAL,
MECHANICAL, PIPING
NON-PROCESS
INFRASTRUCTURE
Kerman provides fully integrated design and construction expertise. Our capability is defined by several key areas, with delivery by traditional means, construct only, design and construct and engineering, procurement & construction (EPC) or Managing Contractor.