Yarnima Project – SMP Completion Works

Location: Newman, WA    Client: BHPB Iron Ore    Project Value: $86M (cost reimbursable)

Yarnima Project SMP Completion (1)

The structural, mechanical, piping (SMP) scope included the completion of the gas turbines 1 and 2; the completion of the piperacks and heavy wall steam pipe; and ƒƒ
construction works on the HRSG’s (heat recovery steam generators) 1, 2 and 3, two steam turbines, two cooling towers as well as associated pipework.

Yarnima Project - SMP Completion Works Yarnima Project - SMP Completion Works Yarnima Project - SMP Completion Works